Security+ Answer Continuity Plan

Here’s the Answer to the Question posted on Facebook

Q. You are helping implement your company’s business continuity plan. For one system, the plan requires an RTO of five hours and an RPO of one day. Which of the following would meet this requirement?

A. Ensure the system can be restored within five hours and ensure it does not lose more than one day of data.

B. Ensure the system can be restored within one day and ensure it does not lose more than five hours of data.

C. Ensure the system can be restored between five hours and one day after an outage.

D. Ensure critical systems can be restored within five hours and noncritical systems can be restored within one day.

Answer available until May 28, 2015.